Oct. 2021 – Dec. 2021
Site preparation
- Demolition of existing structures begin
- Private sector fundraising campaign plans continue
- Programming with the lived-experienced women continues
- Coordination with design and construction team
Jan. 2022 – Dec. 2022
Site preparation continued
- Tender packages and procurement
- Private sector campaign continues
- Programming with the lived-experienced women continues
- Coordination with design and construction team
March 2023
Permits, Tenders and Mobilization
- Building permit and application approvals
- Tender packages and procurement continues
- Mobilization on site
- Continue to clear and grub site
- Construction of buildings begin
Fall/Winter 2023/24
Completion of construction
- Commissioning of all systems, install of telecom and IT systems, phased move-in, final occupancy