Oct. 2021 – Dec. 2021 Site preparation Demolition of existing structures begin Private sector fundraising campaign plans continue Programming with the lived-experienced women continues Coordination with design and construction team Jan. 2022 – Dec. 2022 Site preparation continued Tender packages and procurement Private sector campaign continues Programming with the lived-experienced women continues Coordination with design and construction team March 2023 Permits, Tenders and Mobilization Building permit and application approvals Tender packages and procurement continues Mobilization on site Continue to clear and grub site Construction of buildings begin Fall/Winter 2024/25 Completion of construction Commissioning of all systems, install of telecom and IT systems, phased move-in, final occupancy